THBN
-
THBN:Hadron Accelerators (Contributed)
05 Jun 2025, 11:30 - 12:10
Chair: Prapong Klysubun (Synchrotron Light Research Institute)
THBN1
Commissioning 1.7 MW, 1.3 GeV beam for the proton power upgrade at SNS
With a total project cost of $272 million the recently completed Proton Power Upgrade at the Spallation Neutron Source increased accelerator capability from 1.4 to 2.8 MW, and the first target station from 1.4 to 2.0 MW. 700 kW of beam power will eventually be sent to the Second Target Station. PPU installed 7 high-beta cryomodules, and HPRF to increase the H- linac energy from 1.0 to 1.3 GeV, three new magnets in the accumulator ring to transport 1.3 GeV beam, upgraded utilities throughout the facility, and a new 2.0 MW target design, as well as additional equipment. Installed over several years during semi-annual maintenance outages, equipment was commissioned as it became available. A final PPU-driven 9-month outage began in August 2023 to install the balance of the equipment, and build a tunnel stub that will eventually be extended for the Second Target Station. Following this long outage, SNS was operated at 1.3 GeV for the first time. This presentation will describe the beam commissioning activities following the long outage, and subsequent run, during which the SNS was operated at 1.7 MW on target at 1.3 GeV for 2062 hrs.
  • N. Evans, G. Johns, G. Stephens, J. Moss, K. White, M. Champion, M. Connell, M. Howell, S. Kim
    Oak Ridge National Laboratory
Cite: reference for this paper using: BibTeX, LaTeX, Text/Word, RIS, EndNote
THBN2
FAIR commissioning - Towards first science
2452
The international Facility for Antiproton and Ion Research (FAIR) is under construction at the GSI Helmholtz Centre in Darmstadt. The first project stage includes the superconducting 100 Tm heavy-ion synchrotron SIS100, the Super Fragment Separator, and associated beam transport lines. Part of GSI’s existing accelerator chain, comprising UNILAC and SIS18, will serve as injector. Installation work in the FAIR accelerator tunnels and supply buildings has been ongoing since early 2024. As progress continues, special attention is now on the start of commissioning, beginning in 2025 with the cryogenic plant. Commissioning of the transport line will follow at the end of 2025, and beam commissioning is scheduled for the second half of 2027. This paper outlines the current status of the project, commissioning strategy and timeline.
  • S. Reimann
    Facility for Antiproton and Ion Research, GSI Helmholtz Centre for Heavy Ion Research; Facility for Antiproton and Ion Research, GSI Helmholtz Centre for Heavy Ion Research
  • A. Herlert
    Facility for Antiproton and Ion Research
  • C. Schröder, F. Hagenbuck, H. Simon, H. Albers, H. Kollmus, K. Vogt, M. Kauschke, N. Pyka, O. Geithner, P. Spiller, P. Hofmann, P. Gasik, S. Schwarz, S. Pietri, T. Radon, V. Kamerdzhiev
    GSI Helmholtz Centre for Heavy Ion Research
  • R. Assmann
    Goethe University Frankfurt, GSI Helmholtz Centre for Heavy Ion Research
Paper: THBN2
DOI: reference for this paper: 10.18429/JACoW-IPAC25-THBN2
About:  Received: 24 May 2025 — Revised: 30 May 2025 — Accepted: 02 Jun 2025 — Issue date: 06 Jun 2025
Cite: reference for this paper using: BibTeX, LaTeX, Text/Word, RIS, EndNote